Hockinson School District

In 2023, Hockinson School District selected the Millig Design Build team to improve comfort and reduce operational costs.

Hockinson District Office & Community Center Solutions

At the time of engagement, electric-heating furnaces from’80s served the District Office and Community Center. In addition to being well past their expected service life, these units provided no cooling.

The Millig team replaced the electric furnaces with convertible ducted heat pumps and added ground- and wall-mounted condensing units for energy-efficient cooling.

Hockinson Elementary School Solutions

In 2010, the mechanical systems at the elementary school were modified for increased energy efficiency, and the building’s air-cooled chiller was replaced with an air-to-water heat pump capable of providing both hot and chilled water to the central hydronic loop.

Unfortunately, during swing seasons when the system regularly switched from heating to cooling during the day, the system was unable to provide adequate heating or cooling.

To correct the issue, the Millig team reprogrammed the controls system. The team also replaced all non-LED lighting with high-efficiency LED lighting technology.

Hockinson High School Solutions

Hockinson High School’s Variable Air Volume (VAV) air handlers with electric reheat terminal boxes were in good shape, but its building automation system hadn’t been recommissioned regularly and lighting in the facility was mostly fluorescent.

The Millig team retrocommissioned the building’s existing Automated Logic control system and replaced all non-LED lighting with high-efficiency LED lighting technology.

  • District Office

    Hockinson Community Center

    Hockinson Elementary School

    Hockinson High School

    240,000 total sqft.

  • Energy Savings Performance Contract

  • $751,670

  • $12,876

  • 67 Tonnes CO2e

  • Lauren Donley, Vice President of Business Development

    Scott McVey, PE, Principal-in-Charge

    Josh Slocum, PE, Mechanical Engineer/Cx

    Justin Pape, Sr. Construction Manager

    Deryl Sarver, Sr. Construction Manager

    Cody Majorowicz, Site Superintendent

Hockinson Selects Millig
Millig was helpful and responsive. They walked us through the procurement and grant compliance process, as well as securing utility incentives for the project. We would be happy to work with Millig Design Build again.
— Steve Marshall, Superintendent

OUR SOLUTIONS

  • Heating, ventilation, and air conditioning

  • Smart meters and building controls

  • On-site solar and other renewable energy systems

  • LED lighting retrofits

  • Building envelope improvements

  • Water systems

  • CHP-Cogeneration

  • Building decarbonization

  • And more

CONTACT US